Before the Brick Phila., Pa. Send your plans
460–74 N 2nd Street

161 apartments at 2nd and Noble up for review December 1

A seven-story building with commercial space, a courtyard and a garage underground goes before the city's design panel on December 1. It needs no zoning changes. Here is what's in the plan, and what we'll be listening for.

The plan in 26 seconds, from the air down to the street. Renderings: Ingram/Sageser, animated · Civic Design Review submission, December 2026

Every big building in Philadelphia shows up on paper before it shows up on the street. This one is still on paper. On December 1 it goes to Civic Design Review, the city panel that looks at large buildings before they get their permits.

Street map of the blocks around 2nd and Noble streets. The lot is outlined in a dashed red line at the corner of 2nd and Noble, running back to American Street. The El's Spring Garden stop is marked a block to the north, by I-95.
The lot, dashed, at the corner of 2nd and Noble, running back to American Street. The El's Spring Garden stop is a block north. Map: Before the Brick on Mapbox · © Mapbox © OpenStreetMap · El stop: SEPTA

The plan

The lot is on the corner of 2nd and Noble streets and runs all the way back to American Street, so it has three street fronts. The submission puts it about 500 feet from the Spring Garden El stop. The plan:

  • A seven-story building, 71 feet to the roof.
  • 161 apartments: 25 studios, 114 one-bedrooms and 22 two-bedrooms.
  • Two small commercial spaces on 2nd Street, one at each end, with the main lobby between them.
  • 75 parking spaces underground and 72 bike spaces on the ground floor.
  • An open courtyard with four trees, a green roof and a shared roof deck.
  • Light brick, slatted composite panels around the entrances, and charcoal metal panels.

It needs no zoning variance. The lot is zoned for businesses with apartments above, and there is no height limit. The plan sets aside 10% of the apartments as mixed-income housing, which earns a city bonus to build more floor area. The city has already given it conditional zoning approval. It goes to the design panel because it adds more than 50 homes and more than 50,000 square feet.

Our 3D model of the plan, drawn from its design-review drawings. Drag it to turn it. 3D model: Before the Brick · from the Civic Design Review submission, December 2026
Rendering of the long front of the building on 2nd Street: seven floors of pale brick and dark panels, a wood-slat entrance in the middle, four young trees, and a garage door at the far left.
The 2nd Street front. The main entrance is in the middle, the garage door at the left end. Rendering: Ingram/Sageser · Civic Design Review submission, December 2026

What's there now

A two-story masonry building from 1985 with stores and offices, according to the city's property records. The new building would cover almost four-fifths of the lot.

The city's minimum vs. this plan

City minimumThis plan
Parking6075
Bike spaces5572
Street trees44
HeightNo limit7 floors, 71 ft

The minimums are the plan's own zoning table. Parking counts one space for every three apartments, plus some for the commercial space.

Rendering of the building's entrance at street level: a glass door set in warm wood-look slats under a dark canopy, a bike rack and a tall planter on the sidewalk.
The main entrance on 2nd Street. Rendering: Ingram/Sageser · Civic Design Review submission, December 2026

What we'll be listening for

These are our questions, not the panel's. Its members will raise their own on December 1.

  • TreesFour street trees, exactly the minimum, all on 2nd Street. The drawings say Noble and American streets are too narrow for any.
  • NobleNoble is a small street: 25 feet wide in the city plan, a 15-foot roadway between two 5-foot sidewalks. The building's long side fills the block along it, from 2nd to American, seven stories up.
  • AirThe city's design checklist asks buildings within 1,000 feet of an interstate to put in better air filters (rated MERV 13). The answer here is "N/A." The submission's own map shows I-95 a short way east of 2nd Street, well inside 1,000 feet.
  • EnergyThe same checklist asks for solar or other power made on site, at least 3% of what the building uses. Also "N/A." The green roof is a yes.
  • Cars75 parking spaces, 15 more than the code asks for, about 500 feet from the El.

What happens next

  1. The two-story building on the lot today is built.
  2. Conditional zoning approval is issued, and neighbors get notice of a community meeting.
  3. A virtual community meeting, scheduled by the Northern Liberties Civic Association, the neighborhood group coordinating on this project.
  4. Civic Design Review. The meeting is public; the Planning Commission's meetings page posts the agenda.
  5. The panel sends its recommendations in a letter. They are advice only: the panel can't stop a building that meets the zoning code. Then come the building permits.

We'll be back after December 1 with what the panel said.

Send your plansBook a visitAsk a question

Start with your drawings.We come and measure it.What would you like to know?

We answer within one working day with the price and the date.We answer within one working day with the price and a day for the visit. Nothing to pay now.We answer within one working day.

Which package?
Which one?

    Your drawings stay private. We use them only to price and build your model.We use what you send only to price and book the visit.We use what you send only to answer you.